OPPO Shop@Central Rama2

OPPO Shop@Central Rama2

Another success for us with the OPPO Shop at Central Rama 2. We would like to thank Thai OPPO Co., Ltd. for trusting us with this end-of-year project. We worked quickly to ensure the shop could open before the end of the year, as per the customer’s request.

We received the project in early December and began planning to calculate the timeline to meet our set goals.

We started with the design and obtaining permission from the mall to create the shop, which took only 7-10 days. The first day on-site was December 15th, and the shop opened on December 27th. We completed the shop in just 12 days.

What did we do in those 12 days?

  • Days 1-2: Demolition of the old setup
  • Day 3: Installing the rolling door, painting the grille, and setting up the partition walls
  • Days 4-5: Laying new tiles During the first 5 days, the production team prepared and shaped the walls for installation
  • Days 6-7: Installing the walls designed to meet the customer’s requirements
  • Days 8-10: Electrical system work and painting
  • Last two days: Final touches and detailing for aesthetics